Monte Carlo forecast calculator for software teams
Free Monte Carlo forecaster. Paste your team's weekly throughput and see how many weeks the backlog will likely take, with 50%, 85% and 95% confidence.
How it works
A Monte Carlo forecast answers "when will it be done?" from what your team actually delivered, not from guesses. It replays your past weekly throughput thousands of times in random order and counts how long the backlog takes in each run.
The result is a range with probabilities: the week you'll finish by with 50%, 85% and 95% confidence. Most teams commit to the 85% line.
Want the full method, with examples and common mistakes? Read Forecasting with data: Monte Carlo and #NoEstimates.
Questions people ask
What data do I need?
The number of items your team finished each week for the last 8 to 15 weeks, and the number of items left in the backlog. No estimates are needed.
Do the items need to be the same size?
No. As long as items are split in your usual way, the natural variation in size is already part of the throughput history.
Which percentile should I commit to?
The 85th percentile is a common choice: likely enough to be dependable, without padding the date as much as the 95th.
How often should I re-run the forecast?
Every week. Each new week of throughput makes the forecast sharper, and a changing date is an early warning you can act on.