PERT calculator: three-point estimates with a confidence range
Free PERT three-point estimator. Enter optimistic, most likely and pessimistic guesses to get an expected value and a confidence range.
How it works
PERT turns three guesses into one honest number. Instead of asking "how long will this take?", you ask for the best case, the most likely case and the worst case, then weight them.
The expected value is (optimistic + 4 × likely + pessimistic) / 6. The spread between the best and worst case tells you how uncertain the estimate is, which is often more useful than the number itself.
Want the full method, with examples and common mistakes? Read Estimation techniques compared.
Questions people ask
What is the PERT formula?
Expected = (O + 4M + P) / 6, where O is optimistic, M is most likely and P is pessimistic. The standard deviation is roughly (P − O) / 6.
When should I use PERT instead of story points?
Use PERT for one-off tasks or projects where you need a time range for a stakeholder. Story points work better for comparing work items inside a team that tracks velocity.
How do I get a range I can commit to?
Quote a range rather than a single number. The expected value ± one standard deviation covers roughly 68% of outcomes; ± two standard deviations covers roughly 95%. The calculator shows both.
Why is the pessimistic case so important?
Software estimates are skewed: things rarely finish much early but often finish much late. A realistic pessimistic case is what pulls the expected value towards reality.