Estimation techniques compared: story points, T-shirts, PERT and more
The most common estimation techniques, when to use each, and an interactive PERT calculator.
Key takeaways
- Relative sizing such as story points and T-shirts is fast and good for comparing work.
- Three-point (PERT) estimates express uncertainty explicitly.
- Reference-class forecasting, "how long did similar things take?", is the most underrated technique.
There is no perfect estimation technique, only techniques that fit different questions. Here's a practical guide.
#1. T-shirt sizing
XS, S, M, L, XL. Great for early roadmap conversations where precision would be fake.
- Use when: comparing many ideas quickly.
- Avoid when: someone needs a date.
- Tip: agree on what each size means in your team, e.g. "M is about 1–2 weeks for one person".
#2. Story points and planning poker
Story points measure relative effort and complexity, not time. Teams use Fibonacci-like numbers (1, 2, 3, 5, 8, 13…) because the gaps grow with size, which matches how uncertainty grows.
Planning poker makes it a team sport: everyone picks a card privately, all reveal at once, and the highest and lowest explain their thinking. The discussion is the real value. It uncovers hidden work and misunderstandings.
Tip: Try it with your team for free in our Agile Planning Poker app.
Pitfalls: converting points to hours, comparing velocity between teams, and treating velocity as a performance target.
#3. Three-point estimation (PERT)
Instead of one number, give three:
- O: optimistic, if everything goes well
- M: most likely
- P: pessimistic, if things go wrong (but not a disaster)
The expected value is E = (O + 4M + P) / 6 and the standard deviation is roughly (P − O) / 6.
Use when: a single task or project needs a time estimate with honest uncertainty.
#4. Reference-class forecasting
Ask: "How long did the last five similar projects take?" Then adjust slightly for known differences. It beats bottom-up estimates because history already contains all the surprises you forgot to imagine.
#5. Bottom-up (work breakdown)
Split the work into small tasks, estimate each and add them up. It's useful for finding missing work, but sums of tasks systematically underestimate because integration, rework and coordination hide between tasks. Add a buffer or combine it with reference-class data.
#6. Throughput forecasting
Count finished items per week and simulate the future. No estimating of individual items required. See Forecasting with data: Monte Carlo and #NoEstimates.
#Which one should I use?
| Question | Best technique |
|---|---|
| "Which of these 20 ideas are big?" | T-shirt sizing |
| "What fits in the next sprint?" | Story points / planning poker |
| "How long will this task take?" | PERT three-point |
| "When will this project be done?" | Reference class + throughput forecast |
| "What did we forget?" | Bottom-up breakdown |
Keep reading
The cone of uncertainty, the difference between estimates, targets and commitments, and the habits that make estimates useful.
Use your team's real throughput to forecast delivery dates with probabilities, and try it yourself.
AI makes coding faster, but estimates don't shrink the way you'd expect. Here's how to adjust.