Forecasting with data: Monte Carlo and #NoEstimates

Use your team's real throughput to forecast delivery dates with probabilities, and try it yourself.

Key takeaways

  • Throughput (items finished per week) is a better predictor than estimates.
  • Monte Carlo simulation turns history into probabilities, such as "85% by June 12".
  • Commit at the 85th percentile, not the average.

What if you could skip estimating individual items altogether? Probabilistic forecasting uses what your team actually delivered in the past to predict the future, with honest probabilities.

#The idea in one paragraph

Track how many items your team finishes per week. To forecast a backlog of 40 items, randomly pick a past week's throughput, subtract it from 40, and repeat until the backlog is empty. That's one possible future. Do it 10,000 times and you get a distribution of completion dates.

50%: coin flip85%: commit hereWeeks to finish (10,000 simulated runs using past throughput)
Each bar shows how many of the simulated futures finished in that week.

#Try it

Try it: Monte Carlo forecast5,000 runs
50% chance9 wks
85% chance10 wks
95% chance11 wks

#How to read the result

  • 50th percentile: a coin flip. Don't commit to this.
  • 85th percentile: a good default for commitments.
  • 95th percentile: for things with serious consequences if late.

Remember: "85% likely by week 9" is more honest and more useful than "done in 7 weeks".

#What you need

  1. Throughput history: at least 8–10 weeks is good, and more is better.
  2. Reasonably sized items: not identical, but split anything huge.
  3. A backlog count: plus an allowance for scope growth (often 10–30%).

##NoEstimates, explained fairly

The #NoEstimates movement argues that estimating every item is wasteful when you can forecast from throughput and focus energy on slicing work small. It doesn't mean "never answer when".

Practical version:

  • Slice stories until they take 1–3 days.
  • Stop debating 3 vs. 5 points.
  • Forecast with throughput.
  • Use the time saved to deliver.
#NoEstimates, Allen Holub

#Pitfalls

  • Changing what an "item" means halfway through invalidates history.
  • Ignoring scope growth. Backlogs grow, so model it.
  • Using another team's data. Every team's system is different.

Keep reading

Software estimation

Software estimation fundamentals: why estimates go wrong

The cone of uncertainty, the difference between estimates, targets and commitments, and the habits that make estimates useful.

Software estimation

Estimation techniques compared: story points, T-shirts, PERT and more

The most common estimation techniques, when to use each, and an interactive PERT calculator.

Software estimation

Estimation in the AI era

AI makes coding faster, but estimates don't shrink the way you'd expect. Here's how to adjust.